The regenerator cylinder, the core equipment of Zhejiang Petrochemical Catalytic Cracking Unit, was successfully hoisted into place
On September 9, 2020, the first section of the regenerator cylinder, the core equipment of the second-phase catalytic cracking unit of Zhejiang Petrochemical, which was constructed by the Southwest Branch, was successfully hoisted into place.
The regenerator is the core equipment of the catalytic cracking unit. It arrives in two sections. The first section has a maximum diameter of 12,600mm, a minimum diameter of 7,900mm, a length of 33,550mm, and a weight of 420 tons; the second section is the head plus a section of cylinder, weighing 112 tons. After the regenerator equipment arrived at the site on August 31, the project department carefully organized and made reasonable arrangements. After a week of overtime work to complete the dressing and hating, the hoisting plan node was finally successfully completed.
This hoisting uses a single host to lift the crane For the tail delivery process, the main crane machinery is the XGC16000 1250-ton crawler crane and the tail-sliding crane is the ZCC5200S 400-ton crawler crane. It was officially lifted at 12:30 noon and successfully put into place at 16:30.
After the regenerator cylinder is in place, place Start the installation of equipment internal parts. The regenerator internal parts mainly include main air distribution duct, distributor, large hole distribution plate, cyclone separation system, etc. The total weight of the internal parts of the equipment reaches 329.6 tons, of which the maximum single main air distribution pipe is 35.2 tons. After the cyclone separation system and the second section head of the regenerator are combined, the total weight reaches 402 tons.
The first section of the regenerator cylinder of the catalytic project is hoisted into place, which heralds the project The start of the installation of equipment internal parts will also quickly set off an upsurge in project work, moving towards the goal of “fighting the epidemic and ensuring revenue for two hundred years”.
The compressor unit of Zhejiang Petrochemical Phase II aromatics project was hoisted into place
On August 29, The first equipment K-5301 of the No. 3 aromatics unit centrifugal compressor unit in the second phase of the Zhejiang Petrochemical 40 million tons/year refining and chemical integration project undertaken by the Second Separation and Air Separation Engineering Branch of Zhejiang Industrial Equipment Installation Group Co., Ltd. was successfully hoisted into place.
Zhejiang Petrochemical Aromatics Phase II Project has a total of 6 centrifugal compressors in the 3# aromatics unit and 4# aromatics unit, 4 of which were constructed by the 213 Project Department. In order to safely and efficiently complete the hoisting and construction tasks of the key “heart” unit equipment of the aromatic hydrocarbon plant, the owner, supervisor and project department attach great importance to it. The project department planned in advance and arranged carefully. The site carefully prepared all the preparations before the equipment came into the site and organized technical personnel. Conduct on-site process disclosure and equipment acceptance checks on compressors.
This time the K-5301 compressor unit equipment overall Upon arrival, it consists of the compressor main engine, steam turbine and base. The on-site equipment is unpacked and inspected. The center line of the equipment foundation is marked. The inclined pads are placed in strict accordance with the technical requirements for large-scale unit construction. At about 2 o’clock in the afternoon that day, as the crisp lifting whistle sounded, with the cooperation of a 650-ton truck crane, the 61-ton centrifugal compressor equipment was slowly lifted and slowly crossed the 15-meter steel structure frame of the compressor factory building. The compressor unit was hoisted cleanly and securely on the foundation, creating favorable conditions for the next step of unit adjustment and testing.
Six pieces of equipment for the second phase of the residual oil hydrogenation unit of the Zhejiang Petrochemical Project were successfully shipped
Recently, six pieces of equipment for the Zhejiang Petrochemical Project were successfully loaded at the Erzhong Zhenjiang Company’s heavy-loading terminal and set off for shipment to users.
The 6 pieces of equipment of the Zhejiang Petrochemical Project are the residual oil hydrogenation units of the second phase of the 40 million tons/year refining and chemical integration project of Zhejiang Petrochemical Co., Ltd., including 2 elution towers and hot high-pressure separators. , cold high-pressure separator, circulating hydrogen desulfurization tower/circulating hydrogen desulfurization tower inlet liquid separation tank, circulating hydrogen compressor inlet liquid separation tank, 1 each. The construction of this project is of great significance to promoting the transformation and upgrading of the national petrochemical industry.
In order to ensure that the project is delivered on time, the production and operation department makes overall plans in advance and combines the actual production to sort out the key and difficult issues of the project and formulate reasonable Production Plan. All departments and units worked together and worked overtime to promote production.At the same time, we arranged party member commandos and key personnel to bravely shoulder heavy responsibilities, overcome all important production links, and complete production tasks with quality and quantity.
This project’s circulating hydrogen desulfurization tower/circulating hydrogen desulfurization tower entrance liquid separation tank is the most difficult piece of equipment to be hoisted this time. This product has a special structure and its total length exceeds the width of the workshop axis. Conventional lifting methods cannot meet the shipping needs. After many discussions between the project leader and the auxiliary section, it was finally decided to use two cranes to hoist to the dock for fixed-point steering, and then switch to a single-hook hoisting solution to the ship.
In order to solve the problem of equipment steering, lifting operators and technicians measured site data on site many times and used software to conduct three-dimensional simulated steering. After many attempts, The exact lifting and turning points were determined. On the day of shipment, with the close cooperation of the lifting and driving classes, the steering was finally completed successfully after 12 hours, and the shipment of the product was successfully completed, accumulating successful experience for future shipments of ultra-long equipment.
At present, 6 pieces of equipment for this project have arrived at the user site and are waiting for installation.
The quality assurance node of the four-story substation of the ethylene by-product utilization project is capped
The substation of the Zhejiang Petrochemical Ethylene By-Product Utilization Project, constructed by the Inner Mongolia Branch of China Chemical Engineering No. 11 Construction Co., Ltd., was crowned with the golden dome on August 31, marking the successful realization of another major milestone for the project. Another key achievement was achieved in the activity of “Safeguarding Revenue from the Epidemic and Double Hundred Campaign”.
The The substation is 63 meters long and 30 meters wide. The underground foundation construction includes a total of 160 pile foundations with a pile depth of 4.5 meters. During the construction process of the above-ground part, it was difficult to overcome the continuous rainy weather, which made the overall construction difficult.
On the afternoon of August 31, the owner, supervisor, and construction parties of the substation of the Zhejiang Petrochemical Project completed the acceptance of the top beams, slabs, and columns under the joint witness of the three parties. The pouring was successfully completed in the evening, and the topping was completed. The successful capping of the substation greatly encouraged the enthusiasm of all employees involved in the project, laid a solid foundation for subsequent construction, and more effectively promoted the successful completion of the project construction node period.
Zhejiang Petrochemical’s ethylene project granulation plant breaks ground
On September 1, following the order from the on-site construction commander, the excavator raised its arms and embedded the pliers into the ground. The granulation plant of the Zhejiang Petrochemical Ethylene Project officially started construction, marking the official start of the granulation plant. The construction of the granulation plant for the ethylene project of Zhejiang Petrochemical Company of Inner Mongolia Branch has officially started, marking the first shot of the golden autumn in September.
In the common witness of Derong Chemical Project Manager Mr. Zhou, Jilin Mengxi Supervision Leader, Inner Mongolia Branch Secretary Wang Youming, the main managers of the project department, and the labor team Next, a ground-breaking ceremony was held at the construction site, pushing the project construction into a new climax. The construction has started successfully. All employees of the project department are confident that they will successfully complete the goals in strict accordance with the construction plan.