Key projects are vigorously promoted to help the construction of world-class petrochemical bases embark on a new journey!



On December 25, an on-site observation meeting for the fourth quarter key projects of Lianyungang City’s “High-Quality Development, Later Development, First Arrival” was held in Xuwei New District. Secretary of…

On December 25, an on-site observation meeting for the fourth quarter key projects of Lianyungang City’s “High-Quality Development, Later Development, First Arrival” was held in Xuwei New District. Secretary of the Municipal Party Committee Xiang Xuelong, Mayor Fang Wei and others led the four groups of leaders of the city, as well as the main responsible persons of relevant departments of each county, district and city, to visit the Shenghong Refining and Chemical Integration and Honggang Petrochemical PTA Phase II project sites for on-site observation Construction status of major projects. Miao Hangen, Chairman of Shenghong Group, attended the event and introduced the progress of the project.

The petrochemical industry is a strategic pillar industry for Lianyungang to achieve a new round of development. Shenghong Group has always adhered to The “four first-class” standards promote project construction with high quality, high standards and high speed, helping the port city build a world-class petrochemical industry base. In 2019, Shenghong Group made every effort to promote key projects such as Shenghong refining and chemical integration, Sierbon Petrochemical acrylonitrile technological transformation and capacity expansion, Honggang Petrochemical PTA Phase II, and Rongtai commercial cryogenic storage tanks. Each key project is planned as planned. advance in sequence.

Shenghong Refining and Chemical Integration Project

As the leading project of Lianyungang Petrochemical Base, the financing, design, procurement, construction and other work of Shenghong Refining and Chemical Project are currently continuing to be vigorously promoted. The process package design, overall design, and basic design review have been basically completed, and all orders for ultra-long-cycle equipment have been completed. In November, the civil engineering and installation works of the project began one after another; on December 10, the piling construction of the supporting 300,000-ton crude oil terminal was completed ahead of schedule, laying a solid foundation for subsequent advancement. In 2020, the project will gradually complete the pile foundation and first-level underground pipe construction of the entire plant, long-cycle and regular-cycle equipment ordering, detailed device design, and steel structure construction as planned. The Shenghong Refining and Chemical Project will be accelerated in accordance with the overall goal of handing over the device on June 30, 2021 and commissioning on December 31, 2021.

Silban Petrochemical Acrylonitrile Technology Transformation and Capacity Expansion Project

In order to adapt to the development needs of Lianyungang petrochemical and downstream industries, fully extend the existing industrial chain, and further improve market competitiveness and risk resistance, Sierbon Petrochemical plans to develop acrylonitrile series industries, and in April 2018 Started an acrylonitrile technological transformation and capacity expansion project with a total investment of 3.39 billion yuan. After scientific organization and hard work by all the construction personnel, the project was successfully launched in September this year and has now entered the trial production stage.

Honggang Petrochemical PTA Phase II Project

The Honggang Petrochemical 2.4 million tons/year PTA expansion project has a total investment of 3.858 billion yuan. It adopts internationally leading production technology. After it is put into operation, it will greatly reduce the company’s production costs and improve the company’s industry competitiveness and market share. At present, the main device frame and equipment foundation of the project, as well as part of the single main structure of the building, have been completed. The installation of underground pipe networks and steel structures is in progress. It is expected that 35% of the overall construction progress will be completed within the year. Currently, the project is progressing in an orderly manner in accordance with the target of delivery in October 2020.

Rongtai Commercial Cryogenic Storage Tank

The Rongtai commercial cryogenic storage tank farm project is currently constructing the first phase of storage tanks and supporting storage and transportation facilities. It has built 14 storage tanks with a tank capacity of approximately 257,000 cubic meters. At present, the low-temperature ethylene and low-temperature liquid ammonia projects have completed 75% of the total project volume, and are expected to be completed and put into operation before the end of May 2020; the low-temperature propane and low-temperature butane projects have completed 55% of the total project volume, and are expected to be completed and put into operation by the end of September 2020. It can be completed and put into operation before. </p

This article is from the Internet, does not represent Composite Fabric,bonded Fabric,Lamination Fabric position, reproduced please specify the source.https://www.tradetextile.com/archives/39301