Recently, reporters came to the printing and dyeing park. Relevant personnel from Shantou Zhongsheng Keying Thermal Power Co., Ltd. introduced that so far, the cogeneration project has supplied steam to 30 printing and dyeing companies in the park, and the progress of centralized heating is going smoothly.
Combined heat and power project 1#, Boilers 2# and 3# already have steam supply conditions and have been ignited. The overall debugging and operation of the system has been completed and the formal operation conditions are met. The 1# turbine-generator unit and the 2# turbine-generator unit have been successfully connected to the grid to generate electricity. In terms of thermoelectric steam pipe network, the external pipe network totals about 21,000 meters, of which about 19,800 meters are currently completed; the on-site steam pipe network totals about 350 meters, all of which have been completed.
Li Chenliang, Infrastructure Department Manager of Shantou Zhongsheng Keying Thermal Power Co., Ltd.: We have 3 boilers and 2 boilers in the first phase of our thermal power The turbine-generator unit has now been fully put into operation, and the current daily steam supply of medium pressure plus low pressure can be about 2,000 tons. The heating pipe network on the south side of our thermal power company has completed 90% of the overall progress, and the heating pipe network on the north side of the thermal power company has completed 30% of the overall progress. Currently, there are 30 companies supplying steam. We also hope that printing and dyeing companies can speed up their construction progress, and then we will provide them with good services.
In addition to the cogeneration project, the road pipe network infrastructure project in the printing and dyeing park is also advancing in an orderly manner. At present, 22,260 meters of rainwater and sewage pipes and 21,400 meters of water supply pipes have been completed; the sections of Jing 1st, Jing 5th to 11th, Jing 4th Road, Jing 3rd Road, Wei 1st Road, Wei 6th Road, and Wei 7th Road have been put into trial operation. The pouring along the way has been completed; the construction of other road subgrades, pavement concrete surfaces, trails, street lights, and greening projects is intensifying.
CITIC Environment (Shantou) Printing and Dyeing Environmental Protection Comprehensive Development Co., Ltd. Engineer Zhang Changqiang: The entire road network has about 19 kilometers of roads, as well as sewage pipes, traffic, greening, and lighting. The overall progress is now nearly over 85%. The next step includes (installing) lighting soon, and the greening is almost done. We strive to complete the entire road network as soon as possible and deliver it to the enterprises in the park.
With the gradual improvement of the road network construction in the printing and dyeing park, the District Transportation Bureau also optimized the 502 bus route, added bus stops in the printing and dyeing park, and added a textile center on the basis of the original bus stops. There are 6 pick-up and drop-off points at three stations: Textile 1st Road Station, Textile Middle 2nd Road Station, and Textile South 1st Road Station. This bus adopts segmented fares, with a starting price of 3 yuan and a full journey of 18 yuan.
Liang Zhixiong, member of the Party Leadership Group and Deputy Director of the District Transportation Bureau: Recently, our Transportation Bureau optimized a bus line into the park, which is the 502 bus line, and arranged We have purchased 18 pure electric buses, and there are 56 buses entering the park every day, one every twenty minutes.
The printing and dyeing park has opened bus lines to make travel more convenient for park employees and people along the way. People: There is a bus station here, so it is convenient to travel. When you get home, you can easily take the bus to that bus station.
With the continuous improvement of various infrastructure construction and continuous improvement of service functions in the park, printing and dyeing enterprises have sufficient hardware support to enter the park for production, which will promote the transformation and upgrading of the textile industry, the pillar industry of our region, and accelerate the development of the Lianjiang River Basin. It has played an important role in comprehensive rectification and achieving high-quality economic development.
More news:
“Shantou Development Zone Master Plan” “, proposed that the Chaonan Printing and Dyeing Center will take textile printing and dyeing as the leading industry and develop in the direction of an economic and technological development zone and a provincial industry transfer industrial park. This not only points out the development direction of the Chaonan District Textile Printing and Dyeing Environmental Protection Comprehensive Processing Center, but also makes it more Strengthen Chaonan District’s confidence and determination to build a textile and clothing industry cluster with a value of over 100 billion.
In the “Master Plan of Shantou Development Zone”, the development guidelines for the Textile Printing and Dyeing Environmental Protection Industrial Park (Comprehensive Processing Center) in Chaonan District, Shantou City clearly stated that the construction of key infrastructure should be accelerated. Build an innovative service platform, establish a new model to support the coordinated development of the textile industry chain in Chaonan District, further promote the construction of an independent innovation system with enterprises as the main body, market-oriented, and a combination of industry, academia and research, and promote the development, transformation and upgrading of textile industry clusters, Enhance the core competitiveness of enterprises and upgrade traditional textile manufacturing to advanced manufacturing; promote the development of the underwear and homewear industry and the ability to independently innovate new products, cultivate and develop strategic emerging industries, and strive to create a “mass entrepreneurship and innovation” economic development zone for innovation and entrepreneurship. This is the textile�The Printing and Dyeing Environmental Protection Comprehensive Treatment Center points out the direction of development. </p